Campus educativo — Heredia — Heredia, directed by ICC
Case · Education

Campus educativo — Heredia

Campus expansion of 6,800 m² (classrooms, labs, library) on an operating campus, with mandatory delivery before the academic year start.

Location
Heredia
Area
6,800 m²
Duration
10 months
Delivered
2023

The challenge

Campus expansion of 6,800 m² (classrooms, labs, library) on an operating campus, with mandatory delivery before the academic year start.

The solution

Logistics plan separating construction and student traffic, noisy work restricted to non-class periods.

Results

  • Delivered 14 days before classes started.
  • Zero safety incidents with the student community.
  • MEP operating permit on first attempt.